Construction is moving along. The excavation is nearly completed, and the footings and pads have been poured on a portion of the site. The weather over the last week has slowed us down but we are moving again this week!

Please see tentative updated possession dates below. As a reminder, these are floating ranges of dates and subject to change. You will continue to be updated through our build. We are ahead of schedule which is why you will see that the dates have been moved forward:

East Wing
Floor 1: April – June 2018
Floor 2: May – July 2018
Floor 3: June – August 2018
Floor 4: July – September 2018

West Wing
Floor 1: June – August 2018
Floor 2: July – September 2018
Floor 3: August – October 2018
Floor 4: September – November 2018